The Utica Subway
Last week, Bill de Blasio released a plan for New York’s future called OneNYC, whose section on subway expansion called for a subway under Utica Avenue in Brooklyn (PDF-pp. 45-46). The call was just a sentence, without mention of routing or cost or ridership projections, and no plan for funding. However, it remains a positive development; last year, I put the line at the top of a list of underrated subways in North America. Presumably the route would be a branch off the Eastern Parkway Line, carrying the 4, while the 3 continues to go to the current New Lots terminus.
The cost is up in the air, which means that people forming opinions about the idea don’t have the most important and variable number with which to make decisions. In this post, I am going to work out the range of cost figures that would make this a worthwhile project. This has two components: coming up with a quick-and-dirty ridership estimate, and arguing for a maximum acceptable cost per rider.
Before doing anything else, let us look at how much such a subway extension should cost, independently of ridership. Between Eastern Parkway and Kings Plaza, Utica is 6.8 km. The non-English-speaking first-world range is about $300 million to $3 billion, but around $1.4 billion, or $200 million/km, is average. Utica is a wide, relatively straight street, without difficult development alongside it. In fact, I’ve been convinced in comments that the line could be elevated nearly the entire way, south of Empire Boulevard, which would reduce costs even further. Normal cost should then be around $100 million per km (or $700 million), and even in New York, the JFK AirTrain came in at a $200 million/km. I doubt that an elevated solution could politically happen, but one should be investigated; nonetheless, a $1.4 billion subway would be of great benefit.
Now, let us look at ridership. Recall that Utica’s bus route, the B46, was New York’s third busiest in 2014, with 46,000 weekday riders. But two routes, Nostrand’s B44 and Flatbush’s B41, run parallel and provide similar service, and have 67,000 riders between them. Those numbers are all trending down, as residents gradually abandon slow bus service. A subway can realistically halt this decline and generate much more ridership, via higher speed: B46 limited buses average 13 km/h south of Eastern Parkway, but a new subway line could average around 35 km/h. Second Avenue Subway’s ridership projection is 500,000 per weekday, even though all north-south bus lines on Manhattan’s East Side combined, even ones on Fifth and Madison Avenues, total 156,000 daily riders.
Vancouver is considering replacing its busiest bus, the 99-B, with a subway. The 99-B itself has 54,000 weekday riders, the local buses on Broadway (the 9 and 14) have 43,000, and the 4th Avenue relief buses (the 4, 44, and 84) add another 27,000. Those are much faster buses than in New York: the 99-B averages 20 km/h, while the 44 and 84, running on less crowded 4th Avenue, average nearly 30 km/h west of Burrard. SkyTrain is faster than the New York subway since it makes fewer stops, so the overall effect would be similar, a doubling of travel speed, to about 40 km/h. The ridership projection is 250,000 per weekday in 2021, at opening, before rezoning (see PDF-p. 75 here). This represents a doubling of ridership over current bus ridership, even when the buses provide service SkyTrain won’t, including a one-seat ride from the Westside to Downtown and service along 4th Avenue.
In New York, as in Vancouver, the subway would provide service twice as fast as current buses. The distance between Nostrand and Utica Avenues is much greater than that between 4th Avenue and Broadway in Vancouver, so the analogy isn’t perfect (this is why I also support continuing Nostrand down to Sheepshead Bay). Conversely, the speed advantage of subways over buses is greater than in Vancouver. Moreover, Nostrand already has a subway, so actual demand in southeastern Brooklyn is more than what the B41, B44, and B46 represent. A doubling of ridership over bus ridership, to about 220,000, is reasonable.
For a quick sanity check, let us look at Nostrand Avenue Line ridership again. South of Franklin Avenue, the stations have a combined weekday ridership of 64,000 per weekday, as of 2014. But this is really closer to 128,000 daily riders, counting both boardings and alightings; presumably, few people ride internally to the Nostrand corridor. The Nostrand Avenue Line is 4.3 km long; scaled to length, we get 200,000 weekday riders on Utica.
Put together, a normal-cost Utica Line, with 200,000 weekday riders, would cost $7,000 per rider. This is quite low even by non-US standards, and is very low by US standards (Second Avenue Subway Phase 1 is about $23,000 according to projections, and is lower than most US rail lines).
As far as I’ve seen, from glancing at lines in large cities such as London, Paris, and Tokyo, the normal cost range for subways is $10,000-20,000 per rider. Paris is quite cheap, since its ridership per kilometer is so high while its cost per kilometer is not very high, keeping Metro extensions in the four figures (but Grand Paris Express, built in more suburban geography, is projected at $34 billion for 2 million daily passengers). Elsewhere in Europe, lines north of $20,000 are not outliers. If we set $25,000/rider as a reasonable limit – a limit which would eliminate all US rail lines other than Second Avenue Subway Phase 1, Houston’s light rail extensions, and Los Angeles’s Regional Connector – then Utica is worth $5 billion. A more generous limit, perhaps $40,000 per rider to allow for Second Avenue Subway Phase 2, would boost Utica to $8 billion, more than $1 billion per km. Even in the US, subways are rarely that expensive: the Bay Area’s lines are only about $500 million per km.
The importance of the above calculation is that it is quite possible that Utica will turn out to have a lower projected cost per rider than the next phase of Second Avenue Subway, a project for which there is nearly universal consensus in New York. The original cost projection for Second Avenue Subway’s second phase was $3.3 billion, but will have run over since (the projection for the first phase was $3.7 billion, but actual cost is nearly $5 billion); the ridership projection is 100,000 for each phase beyond the first, which is projected at 200,000. In such a situation, the line would be a great success for New York, purely on the strength of existing demand. I put Utica at the top of my list of underrated transit projects for a reason: the line’s worth is several times its cost assuming world-average per-km cost, and remains higher than the cost even at elevated American prices. The de Blasio administration is doing well to propose such a line, and it is nearly certain that costs will be such that good transit activists should support it.
Quick Note: High Third-World Construction Cost Examples
Dhaka, the world’s poorest megacity (at least until Kinshasa crosses 10 million and qualifies as a megacity), is building a metro system. Using Japanese financing and Indian consultants, it is planning to build a multi-line system, and getting bids for the first line. This line is going to be elevated, and 20-21 kilometers long; construction costs are 220 billion takas, which is $2.8 billion in exchange rate terms and about $8.5 billion in PPP terms.based on the 2013 conversion factor here. This is a bit more than $400 million per kilometer, which is high for a fully underground line, let alone an elevated line.
Jakarta, which is much richer, but still third-world (Indonesia is slightly poorer than China, as of 2014), is building a metro as well. Its first line’s first phase is mixed underground and above-ground: 15.7 kilometers, of which 9.2 are underground. The cost is $1.4 billion, or about $4.2 billion after PPP conversion, giving $266 million per km, still on the high side for a 59% underground line, but nothing as extreme as in Dhaka.
It’s a reminder that poor countries aren’t just low-cost. Things usually are cheaper in the third world, but by a much smaller factor than the income difference. Bangladesh’s GDP per capita, before any PPP conversion, is about $1,000. It is cheaper than the US and Europe, but not by a factor of forty or fifty, but by a factor of about three. Three is an average – imported electronics cost about the same in exchange rate terms everywhere, whereas rent is much more sensitive to local wages – but, for rapid transit construction cost, the average turns out to level the entire difference between the first and third worlds. Some countries, like China, are still a bit cheaper than Europe, while others, like Bangladesh, overshoot.
Why Avoiding Stereotypes is Important (Hoisted from Comments)
In the transit-related forums I participate in, people know that the US builds subways at higher costs than all other countries, because I talk about it often. This feeds into various stereotypes Americans have of government effectiveness; Americans of many political stripes understand that there are serious problems with US governance, and compare the US negatively with certain countries that are famous for getting things done. Thomas Friedman periodically raves about China’s massive infrastructure investment; when he was secretary of transportation, Ray LaHood made the same praise, and connected this to Chinese authoritarianism, while saying that American democracy was still overall a better system. More recently, there’s been praise for Germany, or more generally Northern Europe, as a place with effective infrastructure investment (even as the actual state of German infrastructure is in decline). I was reminded of these stereotypes in the discussion of New York’s shrug-worthy reinvention report at Second Avenue Sagas: once again, the commenters praised the usual-suspect countries, and sometimes connected low construction costs with authoritarianism.
Several more examples from this month have made me notice that people overstate certain cultural differences, especially ones that are in line with stereotypes, such as Western individualism versus Asian collectivism or Northern European efficiency versus Southern European corruption. Cultures are far too diverse to be reduced to these oppositions, and this is especially true on the level of political subcultures, such as transit investment.
The reality is that the places with the lowest construction costs do not really match the stereotypes. Peruse my various posts about subway construction costs again: the main three, but also some of the side ones. Authoritarian countries like China and Egypt do not have unusually low construction costs. Countries with reputations for efficiency run the gamut: Scandinavia and Switzerland are relatively cheap, but Germany and the Netherlands are expensive, with some German projects needlessly expensive because of political influence over alignment choices. Labor costs seem to have a weak if any effect on construction costs: India, by far the poorest country on my lists, is fairly expensive to build in, and within the first world, low-income Naples has cheap construction but so do high-income Swiss cities and middle-to-high-income Milan. Culture in the sense of Samuel Huntington’s civilizations has a weak if any effect, again: there are multiple examples of subway lines built in the Western world, the Islamic world, and East Asia, and the cost differences within each bloc are far greater than the cost differences between the blocs.
I try to avoid giving explanations for these patterns of construction costs. If I knew for certain what caused them, I would not be blogging; I would be forming a consultancy and teaching New York and other high-cost cities how to build subways for less than $100 million per kilometer. I have seen two explanations by professionals. Manuel Melis Maynar, the former CEO of Madrid Metro, explained briefly how Madrid has the world’s lowest construction costs, in terms of design compromises, avoidance of outside consultants, and structuring bids based primarily on technical merit and not cost. And Paul Barter’s thesis explains Japan’s relative lack of urban freeways as a result of high land costs and a costly eminent domain process; this also explains the pattern of Japan’s high urban subway construction costs compared with relatively cheap Shinkansen tunneling (the 50% underground Shin-Aomori extension was only about $55 million per km).
The key here is that neither of these two particular explanations has anything to do with cultural stereotypes of the nations in question. When people think of Hispanic culture, many stereotypes come to mind, but none of them involves having hyper-competent local agencies designing subway systems with small in-house staffs. On the contrary, given the stereotype of Southern European corruption, an American or Northern European who was informed that Madrid Metro awarded contracts based on a combination of technical merit, speed, and cost, and did not use outside consultants, might conclude that it has a bloated in-house staff and that it uses the discretion of technical merit to favor the politically connected. Likewise, although Japan is notorious for the expense of its urban land, it does not have a reputation for strong property rights protections; Anglophone and Western supremacists take it for granted that the West has stronger property rights protections than East Asia, even if in reality English common law makes takings easier than Japanese law.
In addition to the thread on Second Avenue Sagas, in which I felt compelled to constantly defend Southern Europe’s record on building rail infrastructure efficiently, I was recently exposed to another set of stereotypes, in a four-week-old blog post by Andrew McAfee on Financial Times repeating all the usual American exceptionalist tropes of innovation. According to McAfee, the rise of the tech sector of Silicon Valley underscores how the US is going to keep winning the new global economy, giving Tesla as the prime example.
I have a simple bullshit detector for articles about innovation, especially in the tech sector: if they praise Israel’s entrepreneurial cultures, I know with a high degree of certainty that they’re familiar with too small a slice of the nation to be informed. The real Israel, even the upper middle-class slice that I grew up in, is a country at the bottom end of the first world, with Southern Italian average salaries (average household income per capita is about $14,000 a year in PPP terms, about half as high as in the US), with people who move to the US and are floored by the plenty they see at American supermarkets. It has a lot of tech workers, who function as a back office to Silicon Valley, and a handful of inventors who make exit and become rich; neither group is large enough to raise average salaries to proper first-world levels.
But McAfee’s wrongness goes well beyond the line about Israel. In a global economy with specialized regions, people tend to overvalue the sort of production that accords with their sense of identity, and this leads to either regional pride or nationalism. For a certain class of Anglo-American boosters, this is finance; New York and London are global financial centers, and this makes them worthier in this view than cities with different economic roles, such as Paris. McAfee belongs to the class that views the tech sector as the most important, and sees Silicon Valley’s wealth as superior. This is simply the modern equivalent of the 19th-century Manchester boosters’ denigration of Birmingham as a city that didn’t have Manchester’s culture of mass production of cotton, as described in The Economy of Cities; back then the boosters viewed the world as a giant factory, and today they view it as a giant smartphone app. The epitome of this is the overrating of Tesla, which is special only in that it’s made by someone with a background in online companies and not in the auto industry. Who needs the Tokyo rail system when there are luxury electric cars exciting the tech boosters?
As it happens, Europe has a lot of innovation in new fields – it’s not just Siemens making incremental industrial progress; it’s also the Human Brain Project. So do Japan and South Korea: McAfee brushes aside patent statistics, perhaps because Japan and South Korea have by far the highest numbers of patents per capita.
Now, to clarify, it’s possible to relate the US strength in online companies like Facebook to its business culture of superstars, which relates to individualism. In traditional manufacturing sectors, big businesses are built slowly, and require immense amounts of capital; in the tech sector, Mark Zuckerberg could start with a relatively low amount of capital, supplied by an angel investor like Peter Thiel on the strength of an already successful demonstration, and obtain a very large market share via network effects. However, this explanation still requires mediation via business culture. Quoting Marc Andreessen, McAfee lists four explanations, two of which do indeed involve business culture, but two of which play well into the European stereotype of American ignorance: great research universities, and rule of law and respect for contracts and property. Paris has some amazing research universities, judging by the intellectual achievements of their faculty, and as noted above, in some respects the Anglosphere actually has weaker property rights than Japan. But American tech boosters have learned that great universities lead to software and tech businesses, so if the Grandes Ecoles don’t have that then they can’t be that great, right? The national stereotype is stronger than the reality, just as with the insistence of many people in the transit infrastructure debate to talk about China and Northern Europe.
I’m reminded by a point that I made three months ago, in response to a proposal to move Silicon Valley to a growth-friendlier metro area like Houston. Facebook, Uber, and other hot Silicon Valley firms have a culture that works for their industry and that has led to useful inventions. This does not mean that the entire world has to operate like a Silicon Valley firm, nor does this mean that everything in the US operates like one. The same is true of other national stereotypes. The Spanish economy is weak, but happens to have a small segment, corresponding to infrastructure engineering and management, that works very well; other countries would be wise to copy this culture in the realm of infrastructure, and in nothing else, until it can be verified that the same principles work in other settings.
This sort of imitation, focusing on specific aspects of business culture in a particular industry, is harder than general handwaving about how to think like a German or Japanese business manager (a common trope in the 1980s and early 90s) or how to think like a Silicon Valley manager. It requires much more detailed knowledge of several different countries to make comparisons, and this is uncommon, since usually the sort of knowledge that leads to comparative analysis is broader and less specific. I certainly don’t have it – I only know the construction cost output, not the inputs that go into it. Even small mistakes are hazardous: it’s likely that the best performers’ cultures have many distinct features, of which some are crucial to their success but others are irrelevant, and it requires specialized knowledge to sort out which is which.
To add to my previous post about the MTA reinvention report, this is why I’m so disappointed in official efforts to improve American transit governance. The MTA and similar bodies have enough institutional clout and money to hire people who do understand the intricacies of various success stories abroad, and could make specific recommendations, which could appear small but could also be revolutionary. Commentators have to default to first-order information about costs, or to national stereotypes, but the MTA could have detailed knowledge about what’s needed. Instead, the MTA did nothing of the sort, and left the sweeping changes to mongers of stereotypes.
What is the MTA Reinventing, Anyway?
In the last few years New York’s MTA has gone through multiple cycles in which a new head talks of far-reaching reform, while only small incremental steps are taken. The latest is the MTA Transportation Reinvention Commission, which has just released a report detailing all the way the MTA could move forward. Capital New York has covered it and hosts the report in three parts. Despite the florid rhetoric of reinvention, the proposals contained in the report are small-scale, such as reducing waste heat in the tunnels and at the stations on PDF-pp. 43-44 of the first part. At first glance they seem interesting; they are also very far from the reinvention the MTA both needs and claims to be engaging in.
Construction costs are not addressed in the report. On PDF-p. 53 of the first part, it talks about the far-reaching suburban Grand Paris Express project for providing suburb-to-suburb rapid transit. It says nothing of the fact that this 200-km project is scheduled to cost about 27 billion euros in what appears to be today’s money, which is not much more than $150 million per km, about a tenth as much as New York’s subway construction. (Grand Paris Express is either mostly or fully underground, I am not sure.) The worst problem for transit in the New York area is that its construction costs are an order of magnitude too high, but this is not addressed in the report.
Instead of tackling this question, the report prefers to dwell on how to raise money. As is increasingly common in American cities, it proposes creative funding streams, on the last page of the first part and the first six pages of the second part: congestion pricing, cap-and-trade, parking fees, a development fund, value capture. With the exception of congestion pricing, an externality tax for which it makes sense for revenues to go to mitigation of congestion via alternative transportation, all of these suffer from the same problem: they are opaque and narrowly targeted, which turns them into slush funds for power brokers. It’s the same problem as the use of cap-and-trade in California.
One of the most fundamental inventions of modern government is the broad-based tax, on income or consumption. Premodern governments funded themselves out of tariffs and dedicated taxes on specific activities (as do third-world governments today), and this created a lot of economic distortion, since not all activities were equally taxed, and politically powerful actors could influence the system to not tax them. The transparent broad-based tax, deeded to general revenue through a democratic process, has to be spent efficiently, because there are many government departments that are looking for more money and have to argue why they should get it. Moreover, the tax affects nearly all voters, so that cutting the tax is another option the spending programs must compete with. The dedicated fund does neither. If the broad-based tax is the equivalent of market competition, a system of dedicated funds for various government programs is the equivalent of a cartel that divides the market into zones, with each cartel member enjoying a local monopoly. In this way there’s a difference between the hodgepodge of taxes the MTA levies and wants to levy and Ile-de-France’s dedicated 1.4-2.6% payroll tax: the payroll tax directly affects all Francilien workers and employers, and were it wasted, a right-wing liberal politician could win accolades by proposing to cut it, the way New York Republicans are attacking the smaller payroll tax used to fund the MTA.
The proposals of where to spend the money to be raised so opaquely are problematic as well. There is a set of reforms, based on best practices in Continental Europe and Japan, that every urban transit system in the first world should pursue, including in their original countries, where often only some of those aspects happen. These include proof-of-payment fare collection on buses, commuter trains, and all but the busiest subway systems; all-door boarding on buses; mode-neutral fares with free transfers; signal priority and bus lanes on all major bus routes, with physically separated lanes in the most congested parts; a coherent frequent bus network, and high off-peak frequency on all trains; and through-service on commuter rail lines that can be joined to create a coherent S-Bahn or RER system. As far as I can tell, the report ignores all of these, with the exception of the vague sentence, “outfitting local bus routes with SBS features,” which features are unspecified. Instead, new buzzwords like resiliency and redundancy appear throughout the report. Redundancy in particular is a substitute for reliability: the world’s busiest train lines are generally not redundant: if they have parallel alternatives those are relief lines or slower options, and a shutdown would result in a major disruption. Amtrak, too, looks for redundancy, even as the busiest intercity rail line in the world, the Tokaido Shinkansen, has no redundancy, and is only about to get some in the next few decades as JR Central builds the Chuo Shinkansen for relief and for higher speeds.
The only foreigners on the Commission are British, Canadian, and Colombian, which may have something to do with the indifference to best industry practices. Bogota is famous for its BRT system, leveraging its wide roads and low labor costs, and Canada and to a lesser extent the UK have the same problems as the US in terms of best industry practices. Swiss, French, German, Japanese, Spanish, and Korean members might have known better, and might also have been useful in understanding where exactly the cost problems of the US in general and New York in particular come from.
The final major problem with the report, in addition to the indifference to cost, the proposal for reactionary funding sources, and the ignorance of best industry practices, is the continued emphasis on a state of good repair. While a logical goal in the 1980s and 90s, when the MTA was coming off of decades of deferred maintenance, the continued pursuit of the maintenance backlog today raises questions of whether maintenance has been deferred more recently, and whether it is still deferred. More oversight of the MTA is needed, for which the best idea I can think of is changing the cycles of maintenance capital funding from five years, like the rest of the capital plan, to one year. Long-term investment should still be funded over the long term, but maintenance should be funded more regularly, and the backlog should be clarified each year, so that the public can see how each year the backlog is steadily filled while normal replacement continues. This makes it more difficult for MTA chiefs to propose a bold program, fund it by skimping on maintenance, and leave for their next job before the ruse is discovered.
I tag this post under both good categories (“good transit” and “good/interesting studies”) and bad ones (“incompetence” and “shoddy studies”) because there are a lot of good ideas in the report. But none of them rises to the level of reinvention, and even collectively, they represent incremental improvement, of the sort I’d expect of a city with a vigorous capital investment program and industry practices near the world’s cutting edge. New York has neither, and right now it needs to imitate the best performers first.
New York Finds Massive Savings in Transit Construction
MTA Chairman Tom Prendergast announced that an internal review of MTA Capital Construction reveals that there are large wastes in the capital budget that could be eliminated with relatively simple steps. City comptroller Scott Stringer noted that Second Avenue Subway’s first phase, a two-mile stub, costs nearly $5 billion, whereas comparable lines in Paris, London, Tokyo, and other rich, global cities are a fraction of that amount. “Few lines cost more than half a billion dollars per mile,” his office added.
Prendergast’s office directed questions to MTA Capital Construction President Michael Horodniceanu. Horodniceanu outlined a list of items raising New York’s subway construction costs, including labor rules, legal issues, lack of training in new technologies, and insufficient public oversight of contractors. He added that there is little hope of seeing large reductions in the costs of ongoing projects, which are too far advanced, with most of the money already spent, but future subway construction could be done for much cheaper. He did not give a concrete estimate, but a senior official at MTA Capital Construction believed that with the requisite reforms, future subway lines would cost about half a billion dollars per mile in Manhattan and a quarter billion dollars in the Outer Borough.
When asked about the possibility of building Amtrak’s Gateway Project at lower cost, the source qualified those estimates, explaining that Gateway can probably be done for $3 billion, closer to a billion dollars per mile, as much of the project involves underwater tunneling. Officials from Amtrak did not comment on the record by the time this story went to press; however, a senior Amtrak manager speaking on condition of anonymity said, “we don’t really believe this is possible – there are lots of low estimates, and those always lead to budget overruns,” and said that the cost figures from the rest of the world are “irrelevant to America and American labor costs.”
Labor reactions to the announcement were mixed. James Ryan, the president of the Sandhogs Local 147 union, expressed skepticism that costs could be brought down without cutting wages or unionized jobs, and warned of a “race to the bottom” and a “low-wage Wal-Mart economy.” However, he added that he would accept changes as long as there was a guarantee of no job losses, wage cuts, or work rule reforms that would reduce union autonomy. TWU Local 100 President John Samuelsen, whose union represents subway workers rather than construction workers, proposed that the city and the state use the reduced costs to expand subway construction, specifically mentioning future phases of Second Avenue Subway. Currently only Phase 1 is funded, serving the Upper East Side.
Reactions within the state legislature were more positive. The greatest supporter is Assembly Speaker Sheldon Silver (D-Manhattan), whose Lower East Side district is slated to be served by the fourth and last phase of Second Avenue Subway. Silver noted that he was in support of the project even when it was just Phase 1, and said that he would work with the State Senate to pass all the legal reforms requested by Prendergast and Horodniceanu. In the State Senate, co-temporary presidents Dean Skelos (R-Long Island) and Jeffrey Klein (Ind. D-Bronx) had a cooler response. They both praised the revelations and said that they would consider passing the reforms requested, but did not mention any timeline for doing so. Several state legislators, speaking on condition of anonymity, expressed sentiments that the MTA is keeping two sets of books, and if the MTA just admitted to being able to save more money, then its budget requests for operations are also likely suspect. Skelos himself was cool to the proposals for a legislative audit of the MTA, but added, “I understand why people are upset and want to take a closer look.”
In contrast, within City Hall, reactions were overwhelmingly positive. The office of Mayor Bill de Blasio praised Horodniceanu and sent a press release calling MTA Capital Construction’s announcement “a courageous admitting of past mistakes, and an ambitious look forward.” De Blasio himself added that “Now is the time to see where we can build new lines that we thought were unaffordable,” and expressed confidence that all necessary changes can be achieved without running afoul of labor demands.
It is unclear whether the city or the MTA will propose any subway extensions, other than the completion of Second Avenue Subway. In 2008, the MTA’s then-chairman, Elliot Sander, proposed a 22-mile circumferential line running on lightly-used freight rights-of-way, connecting the Bronx, Queens, and Brooklyn without going through Manhattan. Regional Plan Association President Robert Yaro noted that his organization initially proposed this line in 1996 and proposed that the MTA build this line as well as express links to all three airports. He added that this line, which he calls Triboro, requires only about a mile of tunnel and is therefore much cheaper than fully underground lines. “The MTA has found a way to make everything cheaper, both subways and construction on existing infrastructure, so Triboro will be especially cheap now,” he said.
The community groups who could be reached by the article’s deadline were split. Transit activists within Harlem proposed that Second Avenue Subway be modified to add a fifth phase, going crosstown under 125th Street. The members of Harlem’s three community boards agreed that it would be useful, but most of them expressed concerns that it would lead to gentrification and displacement of existing residents, and said they would support the line if the city made an effort to build or preserve affordable housing. MTA planners who spoke on condition of anonymity proposed to extend the 2 and 5 down Nostrand Avenue in Brooklyn and the 4 down Utica Avenue, as per proposals from the 1970s. The response of the community boards in southeastern Brooklyn was more negative, saying that it would change the character of the neighborhoods relatively. One community board member warned that this would lead to “Manhattanization of our neighborhood.”
No member of the New Jersey state government responded to repeated requests for quotes by the article’s deadline.
Empire High-Speed Rail
At the beginning of the month, New York State released its draft environmental impact statement for high-speed rail from New York to the Upstate cities. The costs of HSR as proposed by the state are excessive, and as a result the state has eliminated the high-speed option. It is only considering medium-speed options – the fastest is 125 mph, for the cost of full-fat high-speed rail; it sandbagged the full-speed options. Consider the following passage, from the main document, section 3.2.2:
The dedicated right-of-way of the very high speed (VHS) alternatives would result in significant travel time savings (5:17 and 4:23 respectively for 160 mph MAS and 220 mph MAS), and commensurately higher estimated ridership (4.06 and 5.12 million respectively for 160 mph MAS and 220 mph MAS).
The length of New York-Buffalo is about 690 km. At 4:23, it is an average speed of 157 km/h. To put things in perspective, the Hikari express trains in the 1960s achieved an average of 162 km/h (515 km in 3:10) in 1965, with a maximum speed of 210 km/h.
In section 3.3.5, the 125 mph alternative, which involves greenfield dedicated track from Albany to Buffalo, is said to have an average speed of 77 mph, or 124 km/h. Considering that British express trains on the legacy East Coast and West Coast Main Lines restricted to the same top speed average about 130-140 km/h, this is unimpressive.
Likewise, the cost estimates seem too high. The cost proposed for 125 mph is $14.71 billion. That’s on existing track south of Albany with minor improvements; as per exhibits 3-19 and 3-21, 83% of the cost is said to be Albany-Buffalo, a distance of 380 km on new track plus 76 on existing track. This makes sense for a full-speed, 350 km/h line. But the cost of the full-speed 220 mph option is $39 billion, around $55 million per km from New York to Buffalo in an area with a topography that justifies at most half that.
The study also sandbags the higher-speed options, from 125 mph up, by overplaying the importance of skipped small cities. A greenfield line cannot reasonably serve Schenectady, Amsterdam, and Rome. It could serve Utica, but with some takings because the sharp curve from the tracks at the downtown station to the I-90 right-of-way to the west. Lack of service to Utica would be a drawback, but the study for some reason thinks that those four stations would need their own dedicated intercity line to New York, using a connection to Metro-North, which is said on PDF-p. 37 to have capacity problems on the Hudson Line (the Hudson Line runs 12 trains per hour at the peak today, and is four-tracked). I am told that people drive all the way from Watertown to Syracuse to take Amtrak; none of the skipped four stations is that far from Albany or Syracuse. If a regional train is needed, it can connect at Albany.
The problem is that the alignments studied are uninspiring. I don’t just mean it as a synonym for bad. I mean they avoid locations that look difficult at first glance but are actually reasonably easy. CSX bypasses Albany already; it is not a problem to run high-speed trains at low speed on the existing line between Rensselaer and a spot west of Albany where the line could transition to the Thruway, and yet exhibit 3-20 shows a passenger rail bypass of Albany.
For the full-speed option, I do not know how much tunneling and bridging the state thinks is necessary for its west-of-Hudson I-87 alignment from New York to Albany, but there’s an alignment east of the Hudson with only about 7 km of tunnel, all through the Hudson Highlands. Briefly, such a line would go east of the built-up area in Dutchess County and points north, with a possible station at the eastern edge of the Poughkeepsie urban area and another near Rhinebeck, closer to the city and to the bridge to Kingston than the present Rhinecliff station. In Putnam and northern Westchester Counties, it would utilize the fact that the ridge lines go northeast to southwest to swing to the southwest, to hook up to the Hudson Line slightly north of Croton-Harmon. With a curve radius of 4 km, and a maximum grade of 3.5%, only two tunnels are needed, one under Peekskill of about 2 km and one under the crest in Putnam County of about 5 km. Some additional viaducts are needed through the valleys in the Hudson Highlands, but from Dutchess County north the line would be almost entirely at-grade.
There is generally a tunnel vision in American high-speed rail documents like this, consisting of any of the following features:
– Excessive avoidance of greenfield alignments, even in relatively flat areas. The flip side is excessive usage of freeway rights-of-way. The Syracuse-Rochester segment is actually greenfield in the study, which is good, but there is no thought given to greenfield New York-Albany alignments, which are frankly much easier east of the Hudson than west of the Hudson.
– Questionable assumptions about the abilities of existing track in urban areas to have higher capacity, which often leads to excessive multi-tracking (as in California); there is never any effort to construct an integrated timetable to limit the construction of new tracks.
– No rail-on-rail grade separations. The study talks about Spuyten Duyvil capacity problems, which are very real if traffic grows, but says nothing about the possibility of grade-separating the junction from the Empire Connection to the Metro-North mainline to Grand Central.
– With the exception of California, which erred in the other direction, uninspiring speeds. It’s actually hard to construct a 350 km/h line that only averages 157; actual high-speed lines around the world in the 270+ range average about 180 or higher.
It’s not surprising New York is sandbagging HSR. A year and a half ago, the Cuomo administration killed an HSR study on the grounds that in a recession, the state can’t afford to build such an expensive project. Given how long it takes from the initial study to the beginning of construction, the argument is so transparently wrong that it raises the question of what the real motivation was. But whatever the real reason was, the state is not interested in HSR, and wrote a lengthy environmental impact study to justify its disinterest.
Metro-North-Everything Compatibility
The Regional Plan Association has a new study warning that Metro-North’s infrastructure is falling apart, and demands $3.6 billion in immediate spending on state of good repair. In general, my line on deferred maintenance is “you mean the agency deferred maintenance all those years and didn’t tell us?”. But in this case, despite the language, most of the proposed spending is improvements, namely rehabilitation or replacement of old movable bridges with low speed limits, rather than ongoing maintenance folded into long-term capital spending.
$2.8 billion of the proposed program is for replacing five bridges: Pelham Bay, Cos Cob (over the Mianus), Walk (over the Norwalk River), Saga (over the Saugatuck), and Devon (over the Housatonic). I believe all five should be replaced in the medium term, but the cost proposed is much higher than it should be. $560 million per bridge is quite high, and out of line with Amtrak found on PDF-pp. 29 and 56 of the Northeast Corridor Master Plan. Amtrak cites the cost of replacing the Pelham Bay Bridge alone at $100 million, and the cost of both replacing it and modifying curves on the Hell Gate Line at $500 million. It cites the cost of replacing both the Saga and Walk Bridges at $600 million.
Now, the RPA lists Saga as the easiest bridge to replace since it’s two two-track bridges, so work can be done one bridge at a time with less disruption to ongoing service, but conversely Pelham Bay is also quite cheap according to Amtrak.
But there’s a more serious problem, which is the avoidance of talking about service plans for commuter and intercity rail. If there is serious effort at adding Metro-North service to Penn Station or at raising intercity rail speeds, then the worst speed and capacity restrictions should get priority, and the infrastructure construction should be based on what promotes the desired service plans. It is very expensive and probably cost-ineffective to six-track everything from New Rochelle to Stamford, to allow three speed regimes: local, express, and intercity. I have argued before that it’s better to leave it at four tracks and bypass bad curves, around Port Chester, and make this the six-track segment. This is of course independent of maintenance issues, but suggests which bridge replacements are necessary to support these bypasses (Cos Cob) and which aren’t (the rest are less critical, especially Walk, which intercity trains should bypass on a straighter I-95 segment).
Likewise, there’s a capacity crunch west of Stamford but not one east of Stamford, and this again suggests Cos Cob as the most important priority. Finally, the slowest segment of the NEC away from immediate station areas is the western corner of Connecticut, from the state line to Stamford; Stamford’s curves are mild, while those heading out of Port Chester all the way across the Mianus are quite bad, and straightening the segment would also require straightening the bridge, which can be done easily if it’s replaced. Despite all this, the RPA and Amtrak are saying Cos Cob needs rehabilitation and not replacement, which misses opportunities to both improve reliability and speed up a slow segment.
Moreover, there is no mention of grade-separating Shell Interlocking, just south of New Rochelle. While not a state of good repair issue even in theory, the interlocking’s tight curves impose a limit of either 30 or 45 mph (so, 50-70 km/h), depending on source, in an area that could otherwise support 200 km/h or more. It is very difficult to straighten New Rochelle to sufficient curve radius for that, but 150 requires only minor takings. This may be necessary, independent of speed issues, to raise capacity enough to allow Metro-North service to both Grand Central and Penn Station. It’s possible to schedule trains through the flat junction, but this imposes an additional constraint on the schedule, on top of track-sharing with Amtrak and, in the East River Tunnels, the LIRR.
Monorail Construction Costs
Supporters of monorail and other sleek structures argue that because the structures are thinner than conventional rail viaducts, they’re cheaper and more aesthetic. They even argue that viaducts, which are more expensive than at-grade construction, are actually better. Transrapid does that, and Hyperloop does that as well. Hyperloop proponents specifically mention the the structure’s lighter weight as an explanation for the lower proposed cost – see my post update and the comments for extensive discussion and explanation for why the proposed Hyperloop costs are still an order of magnitude too low to be realistic.
Not having reliable construction costs for the intercity modes, I went and looked for construction costs of urban monorails, which are usually put above-ground, where their sleekness is a major advantage over conventional rail since they do not darken the street as much.
The resource with the most information is a JRTR article about Japanese intermediate-capacity rail, including both monorail and significantly less sleek automated guideway transit (AGT). It includes a diagram of monorail structures, which can be seen to be quite light and thin. The width of the structure from guideway to guideway is 4.5 meters including both guideway widths, and including the outside appears to raise it to 5.5. Two-track elevated conventional rail structures typically range from 7 to 10.5 meters wide.
The most recent Japanese monorail on the list, the Tama Monorail in suburban Tokyo, opened 1998, was $2.422 billion for 16 km: $151 million per km.
The one Japanese project more recent than the JRTR article, the Okinawa Monorail, built from 1996 to 2003, was $1.1 billion for 13 km: $85 million per km. The cost cited on the Monorail Society’s webpage is less than a third that amount. An extension to begin construction soon is projected at $350 million for 4 km, about the same cost per km.
Other Tokyo projects are not cheaper than the Tama Monorail. The AGT Yurikamome, opened 1995, cost $140 million per km as per JRTR; the Tohoku Jukan Line, a conventional elevated structure on top of an older elevated structure located in Central Tokyo, is $400 million for 1.3 km of new el and 2.5 additional km of new track on existing structure, which is $300 million per km if one considers the cost of everything except the new el to be zero, and about $150 million per km if the 2.5 km of existing structure is deemed to cost as much as at-grade rail, which is about half as much as an el typically. The ratio of elevated to underground cost is 2-3 and this is also in line with $150 million per km of baseline cost.
Outside Japan, we have the following projects, with their costs:
Chongqing Rail Transit Line 3: the first phase, built from 2007 to 2011, is ¥13.8 billion for 39 km, or in PPP dollars $88 million per km. About a third of the line is underground. An extension opened in 2013 cost ¥5.7 billion for 16.5 km (Chin.), or $85 million per km, all elevated. This is in a country where fully underground subways average about $150 million per km; but I cannot find cost figures for other lines in Chongqing itself, and any help would be appreciated.
Moscow Monorail: according to Wikipedia, 6.33 billion rubles in 2001-4, or $514 million in 2010 PPP dollars, for 4.7 km. This is $109 million per km, all elevated.
AirTrain Newark: the airport-internal people mover opened in 1996 and cost $354 million for 3 km, while the extension to the mainline train station was built from 1997 to 2000, added another 1.8 km to the project, and cost $415 million; both numbers are taken from the New York Times. Deflating both numbers to 1998, this is $1.03 billion for 4.8 km, or $215 million per km. In contrast, AirTrain JFK, a SkyTrain-like system, was $1.9 billion for 13 km and was built from 1998 to 2002, which in 2010 dollars is $185 million per km, actually lower than the cost of the monorail. Note that the AirTrain construction cost was not that high by normal-world standards: the same technology in Vancouver, in all-elevated configuration, is projected at C$116-150 million per km into Surrey when all elevated (see RRT alternatives 1 and 3 with distances of 15.5 km for 1 and 6 km for 3 as measured on a map), which is about US$95-120 million after PPP conversion. This is a 50-100% premium for New York over Vancouver prices, compared with a 400-600% premium for subway construction.
Palm Jumeirah Monorail, Dubai: Dh4.1 billion for 5.45 km, built 2006-8, about $1 billion in 2010 PPP dollars. This is $183 million per km, all elevated. Compare with the 17% underground Dubai Metro, mentioned in my previous post, which costs half as much per km.
Mumbai Monorail: the master plan is to spend 20,000 crore on 135 km, which after PPP conversion is $66 million per km. The under-construction first line is 3,000 crore for 19.54 km, or $69 million per km, all elevated. This compares with a parallel Mumbai Metro plan to build 146 km for 36,000 crore, or $111 million per km, of which according to Wikipedia 32 km, or 22%, is to be underground. This by itself suggests no monorail cost saving. But the first Mumbai Metro line is already over budget, at 3,800 crore, which again using Wikipedia for length (11.07 km) gives $154 million per km, all elevated. This suggests that in Mumbai there is a cost saving from using monorail, assuming all numbers are correct and that the Monorail Line 1 cost is not just the first phase, which is only 8 km.
Quick Note: Why Quinn is Unfit to be Mayor
The Triboro RX plan calls for using preexisting freight rail rights-of-way with minimal freight traffic to build a circumferential subway line through the Bronx, Queens, and Brooklyn. It was mentioned as a possible project by then-MTA head Lee Sander and more recently by Scott Stringer and on The Atlantic Cities by Eric Jaffe. Despite not having nearly as much ridership potential as Second Avenue Subway or a future Utica subway, the presumed low cost of reactivating the right-of-way makes it a promising project.
According to Capital New York, leading mayoral contender Christine Quinn has just made up a price tag of $25 billion for Triboro, while claiming that paving portions of the right-of-way for buses will cost only $25 million. This is on the heels of city council member Brad Lander’s proposal for more investment in bus service. The difference is that Lander proposed using buses for what buses do well, that is service along city streets, and his plan includes bus lanes on major street and what appears to be systemwide off-board fare collection. In contrast, Quinn is just channeling the “buses are always cheaper than rail” mantra and proposing to expand bus service at the expense of a future subway line.
There is no support offered for either of the two cost figures Quinn is using, and plenty of contradictory evidence. Paving over rail lines for bus service is expensive; a recent example from Hartford and a proposal from Staten Island both point to about $40 million per km in the US. The map in the Capital New York article suggests significant detours away from the right-of-way, including on-street turns making the bus as slow as the existing circumferential B35 route, but also several kilometers on the railroad in Queens. Conversely, reusing rail lines for rail service is not nearly as expensive as building a subway. The MTA’s own biased study says a combined on-street and existing-right-of-way North Shore service would cost 65% more if it were light rail than if it were a busway; since the Triboro right-of-way is intact, the cost of service is in the light rail range, rather than the $25 billion for 35 km Quinn says.
But the reason Quinn is unfit for office rather than just wrong is the trust factor coming from this. She isn’t just sandbagging a project she thinks is too hard; the MTA is doing that on its own already. She appears to be brazenly making up outlandish numbers in support of a mantra about bus and rail construction costs. Nor has anyone else proposed a Triboro busway – she made the logical leap herself, despite not having any background in transit advocacy. Politicians who want to succeed need to know which advocates’ ideas to channel, and Quinn is failing at that on the transit front. If I can’t trust anything she says about transit, how can I trust anything she says about the effectiveness of stop-and-frisk, or about housing affordability, or about the consequences of labor regulations?
Update: Stephen Smith asked Quinn’s spokesperson, who cited a $21 billion figure for a far larger RPA plan including Second Avenue Subway and commuter rail through-running with new lines through Manhattan. I am not holding my breath for a retraction of the bus paving plan from the Quinn campaign.
Update 2: Quinn admitted the mistake on the rail plan, and revised the estimate of the cost down to $1 billion, but sticks to the bus plan and its $25 million estimate.
Comparative Subway Construction Costs, Revised
Here is a list of subway projects in the last 15-20 years, in both developed and developing countries. It’s in addition to my initial lists for developed and developing countries, but includes projects mentioned in past blog posts not on those two lists. This is still not an exhaustive list, due to some cities for which I couldn’t find any information (Moscow), cities for which the information from different sources contradicts itself (Bucharest), and cities for which I couldn’t source numbers beyond Wikipedia (Osaka). My rule is that Wikipedia is an acceptable source for construction timelines and route length but not cost.
While the list is meant to be for urban subways, urban rail projects that are predominantly elevated are also included. As far as possible I have tried using PPP dollars adjusted for inflation to give 2010 dollars (2010 and not 2013, because when I started comparing costs that’s what I used). For core developed countries, because inflation rates are similar, I use American inflation rates, using the CPI (not GDP deflator: the two measures have disagreed for a while, and the CPI points to higher inflation). For other ones, I’ve tried focusing on more recent projects, including even some that are under construction, but I use actual inflation rates.
Bear in mind the data is only as accurate as my sources for it and my PPP conversions. Errors of 10-20% in each direction are to be expected: sources disagree on conversion rates, sometimes the years of construction are not made clear so deflating to the midpoint is not reliable, etc. Even larger errors sometimes crop up, for example if old cost figures are not updated after a cost overrun.
Explicitly, the rates I use today are C$1.25 = S$1 = US$1 = 3.8 yuan = 100 yen = 800 won; £1 = $1.50; €1 = $1.25; CHF1 = $1.65.
Singapore Thomson MRT Line: not yet under construction, expected to open 2019-21, S$18 billion for 30 km. This is $600 million/km, all underground. Included only as a lower bound of costs; costs can rise beyond budget but rarely come significantly under it.
Hong Kong Sha Tin to Central Link: a 1-km segment underground (not underwater) is £270 million, under construction with opening expected in 2018. After converting to PPP using Hong Kong’s conversion rate this is $586 million/km.
Singapore Downtown MRT Line: under construction since around 2008, to be completed in 2017; S$20.7 billion for 42 km: $493 million/km. This line is fully underground. This represents a 70% cost overrun already, announced after I previously reported the original budget of S$12 billion.
Budapest Metro Line 4: under construction since 2006, completion expected in 2014, 400 billion forint for 7.4 km. This is $358 million per km. The line is fully underground.
Fukuoka, Nanakuma Line extension to Hakata: construction expected to begin 2014 with line opening expected in 2020, ¥45 billion for 1.4 km: $321 million/km. I do not know for certain that the extension is fully underground, but this is likely, as the preexisting line is underground and the extension follows busy CBD streets.
Cairo Metro Line 3, Phase 1: opened 2012 with construction since 2006, LE4.2 billion for 4.3 km. This is $310 million/km. The phase is fully underground.
Kawasaki Subway: under construction, opening expected in 2018, ¥433.6 billion for 16.7 km: $260 million/km. The line is fully underground. Update: people in comments explain that the line was actually canceled; the link in this paragraph is just a plan.
Stockholm City Line: to open in 2017, 16.8 billion kronor (2007 prices) for 6 km of tunnel and 1.4 km of bridge: $259 million/km.
Sao Paulo Metro Line 6: construction due to begin in 2014; 7.8 billion reais for 15.9 km: $250 million/km. The line is 84% underground.
Sao Paulo Metro Line 4: construction began in 2004, first phase opened in 2010, completion expected in 2014; 5.6 billion reais for 12.8 km: $223 million/km. The line is fully underground.
Dnipropetrovsk Metro extension: under construction since about 2008, opening expected in 2015, €367 million for 4 km. After PPP conversion this is $214 million/km. It appears to be fully underground.
Malmö City Tunnel: built 2005-10, 9 billion kronor for 4.65 km: $212 million/km. This is a fully underground project.
Bangalore Metro Phase 2: to be opened by 2017, 264 billion rupees for 72.1 km. This is $164 million/km. I do not know what proportion of the project is underground; it does not seem to be large, as the extension of the phase 1 lines are all outbound, and only line 4 seems to have significant tunneling, about 14 km by pure Wikipedia eyeballing.
San Juan Tren Urbano: built 1996-2004, $2.28 billion (2001 figures, see PDF-p. 145) for 17.2 km: $163 million/km. The line is only 7.5% underground by direct inspection on Google Earth.
Lucern Zentralbahn: built 2008-13, CHF250 million for 1.32 km of tunnel: $151 million/km.
Hangzhou: I can’t find any ex post numbers, but in both 2005 and this year (Chinese) officials pegged the cost of future construction as ¥550 million/km: $145 million/km.
Sofia Metro Line 2: built 2008-12, €952 million for 17 km. After PPP conversion, this is $148 million/km. The line appears to be almost fully underground: the numbers here do not fully add up but point to 1.3-2.9 km above ground (7.6-13% of total line length) in one segment while Wikipedia’s line map shows only that segment with above-ground segments.
Thessaloniki: I can’t find any ex post numbers, but in 2005 the budget for the first phase, under construction to be opened in 2016, was €798 million for 9.6 km: $104 million/km. The second phase received bids last year and is expected to open in 2017, with an estimated cost of €518 million for 4.78 km: $135 million/km. Both phases are fully underground.
Vancouver Evergreen Line: under construction since 2012, completion expected 2016; C$1.4 billion for 11 km: $103 million/km. Only 2 km of the system, 18%, is underground, but Vancouver seems to have an unusually low underground construction cost premium.
Dubai Metro (lines 1 and 2): built 2005-11, Dh28 billion ($6.9 billion in PPP2010US$) for 75 km: $92 million/km. Only 13 km of the system, 17%, is underground.
Mexico City Metro Line 12: built 2007-2012, $1.8 billion for 26.4 km. After PPP conversion, this is $90 million/km. From a Google Earth overlay map, this line is 49% underground.
Seoul Sin-Bundang Line: built 2005-11, 1,169 billion won for about 18 km (sources disagree on whether it’s 17.3 or 18.5): $87 million/km. The line is 100% underground according to YouTube videos.
Bangalore Metro, Phase 1: built 2006-11, 8,158 crore rupees for 42.3 km: $93 million/km. Only 8.82 km, or 21% of the project, is underground. See above for Indian construction costs in a heavier-tunneling setting.
Helsinki Westmetro: under construction since 2009 with completion expected in 2015, €714 million for 13.5 kilometers: $66 million/km. The line is fully underground.
Seoul Subway Line 9: opened 2009, 900 billion won for 27 km: $43 million/km. The line is almost fully underground by direct inspection on Google Maps.
Barcelona Sants-La Sagrera tunnel: built 2008-11, €179.3 million for 5.8 km: $39 million/km. This project is intercity but fully underground.
Just from eyeballing the data, spliced together with the two older lists, the biggest correlation of each country’s construction costs is with the construction costs of other lines in the same country. When there is more than one project listed separately in a city – e.g. Seoul, Singapore, Sao Paulo – the projects have similar costs. This persists across different cities in the same country, judging by the similarity between Bangalore Metro’s Phase 2 cost and the Delhi Metro’s cost from a previous list and by the similarity between Hangzhou and Beijing’s costs.