The TransitMatters Rail Electrification Report
At TransitMatters, we’ve just released a report about the costs and benefits of rail electrification. It’s anchored to our proposal to electrify and modernize the commuter rail system in the Boston area, but much of the analysis is broader than that. The non-Bostonian reader may still be interested in the description of construction costs of electrification and the short case studies of Israel, Denmark, Norway, New Zealand, Britain, Canada, and the United States. The latter two, covering Toronto and the Bay Area, are unusually expensive and we go over why that came to be and how it is possible to avoid them. The section on alternatives and why they are all inferior to stringing wire and running EMUs is of general interest as well, and I hope European policymakers read over and take it as a sign they should electrify more lines (ideally, all of them, as is being done right now in South Korea, India, and China).
The Toronto problem
When we came up with the cost range of $800 million to $1.5 billion, there was a lot of skepticism. The Reddit thread‘s two most common kinds of comment are “great, this can’t happen fast enough” and “it will cost billions because of unspecified MBTA problems.” As I said in responding to one of the comments, the higher-cost comparison cases all have specific reasons for their higher costs: Britain has clearance restrictions that do not exist anywhere else in the world, and Caltrain had unusual managerial incompetence regarding the related signaling project where the MBTA is actually doing well. But Toronto still looms large.
As I said on Reddit,
I’m not too worried about Caltrain’s errors, which were truly bespoke. Toronto worries me more, because while the specifics are avoidable, the ultimate cause is reproduced: Toronto and Boston are both huge cities with heavy peak commuter rail traffic and should have electrified generations ago, so now the benefits of electrification are so high that managers can afford to be careless about costs and still have above-water benefit-cost ratios.
So it is important to be careful and avoid Toronto’s problems with cost control. This means baking cost control into the program from the start, and aggressively protecting the budget from use by other actors as OPM:
- The budget should be set at a standard level with standard contingencies. Do not aim for the ceiling; aim for average. Nor should anyone include 100% contingency as used by Toronto; if you budget money for the project it will be used, so optimize for minimizing overall cost rather than for just-in-case funding.
- Designs should be standard, and variations should be accommodated only based on cost minimization. Basically, if it’s good enough for Germany, France, Denmark, Norway, Israel, etc.,, it’s good enough for the United States.
- If NIMBYs push back, the state should fight back. They want noise walls? Nope, EMUs are a lot quieter than diesels, quality of life will improve. They want trenches? Nope, that’s too expensive.
- Under no circumstances should passenger rail electrification money be used for corporate welfare for freight rail companies. They can pay their own way for clearance for double-stacked containers.
The importance of maximum electrification
Based on the observations that the lifecycle costs of DMUs are about twice those of EMUs, and that operating and capital costs are both driven by the peak rather than off-peak, it’s possible to establish financial rates of return on electrification. Not counting the speed and reliability benefits to passengers, the ROI is around 0.3-0.5% per US-size car per hour at the peak. Lines that run 8-car trains every 15 minutes at rush hour run 32 cars per hour and so have an ROI of 10-16%; this is why outside the US and Canada, cities that run such long trains at such frequency have long electrified their tracks.
The problem is that electrification is relatively unfamiliar in North America. It exists, but is sporadic, and there have been very few recent projects, so managers think it’s a Herculean task. In Boston I’ve seen reticence to wire more track due to institutional conservatism, even in plans that spend comparable amounts of money on things the region is more used to, like station platform upgrades and extra tracks. Worse, I’ve seen this in New Jersey, which is largely already electrified but uninterested in finishing the job.
Against such conservatism, it’s important to remember that failure to undertake a high-value investment isn’t any more moral than a large investment that goes to waste. When your ROI hits double digits, you waste public benefits by avoiding or even just delaying the project – and the above calculation comes just from savings on operating, maintenance, and capital acquisition costs, without the large benefits to passengers, the environment, etc.
Can large cities afford not to electrify? Yes. They have money for many kinds of waste, including for forgoing the benefits of commuter rail electrification. But just because they can afford to waste money and social benefits doesn’t mean they should. So, please, no talk of DMUs, or bi-modes, or pilot programs, or batteries – just wire your system already and import some high-quality EMUs.